March 2025 – Construction Update

March 28, 2025

Construction at Chronicle is progressing smoothly. The concrete work is in its final stages, with just 2-3 weeks remaining. The heritage home will soon be returned to the site within the same timeframe.

Meanwhile, foundation backfilling is ongoing, and wood framing is set to begin shortly. With steady progress, we’re in a race to get the roof on–stay tuned as Chronicle continues to take shape!

read more

January 2025 – Construction Update

February 4, 2025

The first concrete slab has been poured, and work on the second slab is moving along smoothly. This includes building the framework, adding reinforcement, and preparing for the next concrete pour.

With the foundation now complete, construction on the elevated slab has begun.

read more

December 2024 – Construction Update

December 13, 2024

Main slab poured:
The primary foundation is complete, providing a solid base for further construction.

Walls stood up and concrete poured:
Structural walls have been raised.

Parkade columns are set for pour:
Work on the underground parking structure is well underway, with columns now in place.

read more